Sprinkler upgrade project in Main Building starts Dec. 5 & continues in spring

Dec 2, 2022

As part of the final phase in completing the new Health Simulation (SIM) Lab, an upgrade to sprinkler systems throughout the Clifton Campus Main Building will begin on Monday, December 5.

This project will include the first, second, and third floors of the Main Building, and is scheduled to conclude in March 2023.

During the project, some unavoidable, intermittent hammering and drilling noise will occur as new piping is installed, and some materials may need to be placed in hallways prior to installation.

  • All efforts will be made to keep construction noise to a minimum during times classes are in session, especially during the final week of Fall Semester.
  • Construction work is limited to hallways and corridors, and will involve removing ceiling tiles and then working overhead.
  • Work on the 1st floor is projected to be completed in January, the 2nd floor in February, and the 3rd floor in March. However, the projected schedule may be need to adjusted as work progresses. Updates to the College community will be provided as needed.
  • Safety considerations will be given utmost importance throughout the project. 

If you have questions or concerns, please reach out to Kim Vasko, Director of Buildings, Maintenance & Grounds (kimberly.vasko@cincinnatistate.edu or call Kim’s cell at (513) 673-0348).

The Facilities Department appreciates help from College faculty and staff member in providing temporary storage space for project materials and in coordinating equipment moves to get the project off to a good start. Thanks go to Bill Mehbod, Drew Tenhundfeld, Shawn Stacy, Ann Gunkel, and Lisa Bacu.